4 a. If the NPV (Net Present Value) of a project is positive, then the project\'
ID: 2801101 • Letter: 4
Question
4
a.
If the NPV (Net Present Value) of a project is positive, then the project's IRR (Internal Rate of Return) ____________ the required rate of return/cost of capital of the project.
cannot be determined without actual cash flows
could be greater than or less than
must be less than
none of the above.
V. must be greater than
b.
Consider the following two projects:
Time Cash Flows
A B
0 -$4,000 -$4,000
1 $2,003 $0
2 $2,003 $0
3 $2,003 $0
4 $2,003 $10,736
Assuming a 14 percent discount rate, which project would you prefer?
Hint: Use NPV method
Project A, because it has a higher IRR
Project B, because it has a higher IRR
III. Project A, because it has a higher NPV
Project B, because it has a higher NPV
None of the above
I.cannot be determined without actual cash flows
II.could be greater than or less than
III.must be less than
IV.none of the above.
V. must be greater than
b.
Consider the following two projects:
Time Cash Flows
A B
0 -$4,000 -$4,000
1 $2,003 $0
2 $2,003 $0
3 $2,003 $0
4 $2,003 $10,736
Assuming a 14 percent discount rate, which project would you prefer?
Hint: Use NPV method
I.Project A, because it has a higher IRR
II.Project B, because it has a higher IRR
III. Project A, because it has a higher NPV
Project B, because it has a higher NPV
V.None of the above
Explanation / Answer
a.
Option ii.
IRR and NPV need not lead to the same decision. Even when NPV is positive IRR can be either greater or less than cost of capital. This is because they both are different measures, while NPV is the cashflow, IRR is the discount rate.
b.
NPV is calculated by discounting the cashflows
PV = C/(1+r)^n
C - Cashflow
r - Discount rate
n - years to the cashflow
Project A:
NPV = -4000 + 2003/(1+0.14)^1 + 2003/(1+0.14)^2 + 2003/(1+0.14)^3 + 2003/(1+0.14)^4 = $1836.17
Project B:
NPV = -4000 + 10736/(1+0.14)^4 = $2356.57
Option iV.
Choose project B, because it has a higher NPV
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.