You are getting ready to start a new project that will incur some cleanup and sh
ID: 2800971 • Letter: Y
Question
You are getting ready to start a new project that will incur some cleanup and shutdown costs when it is completed. The project costs $5.35 million up front and is expected to generate $1.17 million per year for 10 years and then have some shutdown costs at the end of year 11. Use the MIRR approach to find the maximum shutdown costs you could incur and still meet your cost of capital of 14 8% on this project. The maximum shutdown costs allowable to still have a positive NPV is S(Round to the nearest dollar.)Explanation / Answer
Given,
Project Cost = $5.35 Million
Inflows = 1.17 per year
10 years life
Cost of Capital = 14.8
Sume Pv's of 10 years @ 14.8% is 5.06
By multiplying yearly inflows with sum of pv
1.17*5.06 = 5.92
So NPV is 5.92-5.35 = 0.57 Millions
11th year PV factor is 0.219
The maximum shutdown costs allowable to still have a positive NPV is 0.57/0.219 = $2.59 Millions
If the shut down cost is less than the $2.59 Million then NPV will be in positive
Year Cash Flows PV factors @ 14.8 PV of Cash flows 0 -5.35 1 -5.35 1 1.17 0.87108 1.02 2 1.17 0.758781 0.89 3 1.17 0.660959 0.77 4 1.17 0.575748 0.67 5 1.17 0.501523 0.59 6 1.17 0.436866 0.51 7 1.17 0.380546 0.45 8 1.17 0.331486 0.39 9 1.17 0.288751 0.34 10 1.17 0.251525 0.29 11 -2.59 0.219098 -0.57 NPV 0.00Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.