#5) Gomi Waste Disposal is evaluating a project that would cost 70,300 dollars t
ID: 2784539 • Letter: #
Question
#5) Gomi Waste Disposal is evaluating a project that would cost 70,300 dollars today. The project is expected to produce annual cash flows of 6,260 dollars forever with the first annual cash flow expected in 1 year. The NPV of the project is -18,904 dollars. What is the cost of capital of the project? Answer as a rate in decimal format so that 12.34% would be entered as .1234 and 0.98% would be entered as .0098.
#6) Fairfax Pizza is evaluating a project that would cost 7,744 dollars today. The project is expected to have the following other cash flows: 2,164 dollars in 1 year, 2,049 dollars in 3 years, and 6,577 dollars in 4 years. The NPV of the project is -81. What is the internal rate of return for the project? Answer as a rate in decimal format so that 12.34% would be entered as .1234 and 0.98% would be entered as .0098.
Explanation / Answer
1
Let r be the cost of capital
So, NPV=-70300+6260/(1+r)+6260/(1+r)^2..........
Hence, NPV=-70300+6260/r
Given, NPV=-18904
So, -70300+6260/r=-18904
=>+70300-18904=6260/r
So, cost of capital, r=12.18%
2
IRR is the rate at which NPV=0
So,
0=-7744+2164/(1+r)+2049/(1+r)^3+6577/(1+r)^4
r=11.17%
Hence, IRR=11.17%
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.