Project S costs $19,000 and its expected cash flows would be $5,000 per year for
ID: 2769767 • Letter: P
Question
Project S costs $19,000 and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L costs $38,000 and its expected cash flows would be $14,300 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend?
Select the correct answer.
I. Project L, since the NPVL > NPVS.
II. Both Projects S and L, since both projects have IRR's > 0.
III. Project S, since the NPVS > NPVL.
IV. Both Projects S and L, since both projects have NPV's > 0.
V. Neither S or L, since each project's NPV < 0.
Explanation / Answer
Solution:
The answer to the above question is -
I. Project L, since NPVL > NPVS
Project S Year 0 Year 1 to 5 Initial Investment -19,000 Cash inflows 5,000 PVAF @ 15 % for 5 years 3.791 Present value of cash inflows 18,953.93 Total present value of cash inflows 18,953.93 NPV = Total present value of cash inflows - Initial investment - 46.07 Project L Year 0 Year 1 to 5 Initial Investment -38,000 Cash inflows 14,300 PVAF @ 15 % for 5 years 3.791 Present value of cash inflows 54,208.25 Total present value of cash inflows 54,208.25 NPV = Total present value of cash inflows - Initial investment 16,208.25Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.