Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Louise Manufacturing uses 2,600 switch assemblies per week and then reorders ano

ID: 2766515 • Letter: L

Question

Louise Manufacturing uses 2,600 switch assemblies per week and then reorders another 2,600. The relevant carrying cost per switch assembly is $10.50, and the fixed order cost is $1,300. What are the current carrying costs? (Do not round intermediate calculations.) Carrying costs $ What are the order costs? (Do not round intermediate calculations.) Order costs $ Calculate the economic order quantity. (Do not round intermediate calculations and round your final answer to 2 decimal places, e.g., 32.16.) EOQ

Explanation / Answer

a. Total Carrying costs = 2600*10.50 = 27,300

b. The total order costs are 1300 for 52 weeks = 1300*52 = 67,600

c. The EOQ is calculated as follows:

EOQ = sqrt (2*T*F/CC)

T = 2600*52 = 135200, F = 1300 and CC =10.50

Hence EOQ = sqrt (2*135200*1300/10.50) = 5786.025 units = 5,786.03 Units