Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Louise Manufacturing uses 2,600 switch assemblies per week and then reorders ano

ID: 2742216 • Letter: L

Question

Louise Manufacturing uses 2,600 switch assemblies per week and then reorders another 2,600. The relevant carrying cost per switch assembly is $10.50, and the fixed order cost is $1,300.

  

  

  

  

  

Calculate the economic order quantity. (Do not round intermediate calculations and round your final answer to 2 decimal places, e.g., 32.16.)

  

Louise Manufacturing uses 2,600 switch assemblies per week and then reorders another 2,600. The relevant carrying cost per switch assembly is $10.50, and the fixed order cost is $1,300.

Explanation / Answer

1) Current Annual Carrying Cost = Current Average Inventory * Unit Cost (in $) * Carrying Cost (%)

In this particular question the Carrying cost per unit is directly given in $, hence the formula would be modified to

Current Annual Carrying Cost = Current Average Inventory * Carrying Cost per Unit (in $)

Current Annual Carrying Cost = 2600/2 * $10.50

Answer – Current Annual Carrying Cost = $13650

2) Current Order cost here is $1300 per order fixed cost

In an year, total number of orders would be 52

Hence Current Annual order cost = Number of orders * Order cost

Current Annual order cost = 52 * $1300

Answer - Current Annual order cost = $67600

3) Economic Order Quantity (EOQ) = SQRT (2*D*S/H)

D = Annual Demand (Units) = 2600 per week * 52 = 135200 Unit Per Year

S = Cost per order = $1300 per order fixed

H = Holding cost (in $) = $10.50

Economic Order Quantity (EOQ) = SQRT (2*135200*$1300/$10.50)

Answer - Economic Order Quantity (EOQ) = 5786.03