A scoping study was recently conducted by senior ChE students on the feasibility
ID: 2762564 • Letter: A
Question
A scoping study was recently conducted by senior ChE students on the feasibility of constructing an oil refinery in Houston, Texas to process West Texas Crude. The students determined that the construction of the facility will take 4 years. The capital costs will therefore be spread amongst these according to the following schedule:
Year
Capital Cost
-3
-2
-1
0
($83 million)
($250 million)
($250 million)
($370 million)
The following annual costs (in millions) were estimated for the project:
Annual cost
Raw materials
Labor
Maintenance
Utilities
$9,700
$0.89
$57
$24
The annual revenue is predicted to be $12,000 million and the project is expected to last for 20 years with no expected salvage value. The capital equipment will be depreciated using the 10 year MACRS schedule. Please use a federal tax rate of 35% and state tax rate of 1%.
If the company’s MARR is 18%, determine the after tax NPV and after tax RoR.
Conduct sensitivity analyses to determine the magnitude of the economic hazards (choose several variables) associated with this project.
Please show all work
Year
Capital Cost
-3
-2
-1
0
($83 million)
($250 million)
($250 million)
($370 million)
Explanation / Answer
Yearly Profit Million $ Sales 12,000 Less:- Cost Raw Material 9,700 Labor 1 Maint 57 Utilities 24 Total Cost 9,782 Profit 2,218 Project Cost = $ 83+ $250+$250 + $370= $ 953 Million 10-year Depreciation 1 10 95.30 2 18 171.54 3 14.4 137.23 4 11.52 109.79 5 9.22 87.87 6 7.37 70.24 7 6.55 62.42 8 6.55 62.42 9 6.56 62.52 10 6.55 62.42 11 3.28 31.26 Calculation of NPV Year Intial Out flow Profit Tax Saving on Dep Tax on Profit @35% State Tax @ 1% Net Cash Flow Discount Factor @ 18% NPV -3 -83 -83 1.64 -136.37 -2 -250 -250 1.39 -348.10 -1 -250 -250 1.18 -295.00 0 -370 -370 1 -370.00 1 2,218 33.36 -776 -120 1,355 0.847 1,148.41 2 2,218 60.04 -776 -120 1,382 0.718 992.39 3 2,218 48.03 -776 -120 1,370 0.609 833.70 4 2,218 38.42 -776 -120 1,360 0.516 701.57 5 2,218 30.75 -776 -120 1,353 0.437 591.20 6 2,218 24.58 -776 -120 1,346 0.370 498.73 7 2,218 21.85 -776 -120 1,344 0.314 421.80 8 2,218 21.85 -776 -120 1,344 0.266 357.45 9 2,218 21.88 -776 -120 1,344 0.225 302.93 10 2,218 21.85 -776 -120 1,344 0.191 256.72 11 2,218 10.94 -776 -120 1,333 0.162 215.79 12 2,218 -776 -120 1,322 0.137 181.37 13 2,218 -776 -120 1,322 0.116 153.71 14 2,218 -776 -120 1,322 0.099 130.26 15 2,218 -776 -120 1,322 0.084 110.39 16 2,218 -776 -120 1,322 0.071 93.55 17 2,218 -776 -120 1,322 0.060 79.28 18 2,218 -776 -120 1,322 0.051 67.19 19 2,218 -776 -120 1,322 0.043 56.94 20 2,218 -776 -120 1,322 0.037 48.25 6,092.17
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.