#3 Suppose you calculate the Internal Rate of Return (IRR) for a project, given
ID: 2758096 • Letter: #
Question
#3
Suppose you calculate the Internal Rate of Return (IRR) for a project, given the project cash flows and a required rate of return of 12%. After you calculate the IRR, you discover that the actual required rate of return is 14%. The new IRR you calculate using a required rate of return of 14% would be
a. lower than the IRR calculated with a required rate of return of 12%.
b. higher than the IRR calculated with a required rate of return of 12%.
c. the same as the IRR calculated with a required rate of return of 12%.
d. uncertain because it could be either lower or higher than the IRR calculated with a required rate of return of 12%.
a. lower than the IRR calculated with a required rate of return of 12%.
b. higher than the IRR calculated with a required rate of return of 12%.
c. the same as the IRR calculated with a required rate of return of 12%.
d. uncertain because it could be either lower or higher than the IRR calculated with a required rate of return of 12%.
Explanation / Answer
Ans C : The same as the IRR caclulated with a required rate of return 12%
IRR is calculated irrespective of cost of capital. While calculating IRR required rate of return is not considered.
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.