NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considerin
ID: 2750203 • Letter: N
Question
NPVs, IRRs, and MIRRs for Independent Projects
Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $19,000, and that for the pulley system is $20,000. The firm's cost of capital is 12%. After-tax cash flows, including depreciation, are as follows:
Calculate the IRR for each project. Round your answers to two decimal places.
Truck: %
What is the correct accept/reject decision for this project?
-Select-AcceptRejectItem 2
Pulley: %
What is the correct accept/reject decision for this project?
-Select-AcceptRejectItem 4
Calculate the NPV for each project. Round your answers to the nearest dollar, if necessary. Enter each answer as a whole number. For example, do not enter 1,000,000 as 1 million.
Truck: $
What is the correct accept/reject decision for this project?
-Select-AcceptRejectItem 6
Pulley: $
What is the correct accept/reject decision for this project?
-Select-AcceptRejectItem 8
Calculate the MIRR for each project. Round your answers to two decimal places.
Truck: %
What is the correct accept/reject decision for this project?
-Select-AcceptRejectItem 10
Pulley: %
What is the correct accept/reject decision for this project?
Explanation / Answer
Year Truck Pulley 0 (19,000) (20,000) 1 to 5 5,100 7,500 PV annuity factor 12% 3.605 3.605 PV of cash inflow 18,384 27,036 NPV (616) 7,036 Decision reject accept PV annuity factorTruck - 11%, pulley 25% 3.6960 2.6890 18,850 20,168 IRR 11% 25% Decision reject accept
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.