Budgeted cost of direct materials at 350,000 units $ 525,000 Budgeted cost of di
ID: 2736916 • Letter: B
Question
Budgeted cost of direct materials at 350,000 units
$ 525,000
Budgeted cost of direct materials at 325,000 units
$ 487,500
Actual cost of direct materials at 350,000 units
$ 612,500
Actual level of output (units)
350,000
Planned level of output (units)
325,000
What is the direct material quantity variance? You must include your calculations.
Budgeted cost of direct materials at 350,000 units
$ 525,000
Budgeted cost of direct materials at 325,000 units
$ 487,500
Actual cost of direct materials at 350,000 units
$ 612,500
Actual level of output (units)
350,000
Planned level of output (units)
325,000
Explanation / Answer
We can see here that both budgeted and actual level of inputs are same, therefore, material quantity variance would be:
Standard price per unit = budgeted cost / no. of units
= 525,000 / 350,000
= 1.50
Material quantity variance = (Standard quantity – actual quantity) x Standard price
= (325,000-350,000) x 1.50
= 37,500 unfavorable
So material quantity variance would be 37,500 unfavorable.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.