LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its be
ID: 2730818 • Letter: L
Question
LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects have a WACC of 8%, and its above-average risk projects have a WACC of 12%. Which of the following projects (A, B, and C) should the company accept?
Project B, which is of below-average risk and has a return of 8.5%.
Project C, which is of above-average risk and has a return of 11%.
Project A, which is of average risk and has a return of 9%.
None of the projects should be accepted.
All of the projects should be accepted.
a)Project B, which is of below-average risk and has a return of 8.5%.
b)Project C, which is of above-average risk and has a return of 11%.
c)Project A, which is of average risk and has a return of 9%.
d)None of the projects should be accepted.
e)All of the projects should be accepted.
Explanation / Answer
Every company takes the decision to accept the project with lower risk and higher return or the project with return higher than the cost of capital.
A
Here Project B has the lower risk i.e., below average risk and return (8.5%) is greater than the WACC (8%). Hence Project B should be accepted.
Correct Option is a) Project B, which is of below average risk and has a return of 8.5% should be accepted.
Project WACC ReturnA
10% 9% B 8% 8.5% C 12% 11%Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.