LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its be

ID: 2705916 • Letter: L

Question

LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects have a WACC of 8%, and its above-average risk projects have a WACC of 12%.  Which of the following projects (A, B, and C) should the company accept? Answer                                         
           Project B, which is of below-average risk and has a return of 8.5%.                             
           Project C, which is of above-average risk and has a return of 11%.                             
           Project A, which is of average risk and has a return of 9%.                             
           None of the projects should be accepted.                             
           All of the projects should be accepted. LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects have a WACC of 8%, and its above-average risk projects have a WACC of 12%.  Which of the following projects (A, B, and C) should the company accept? LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects have a WACC of 8%, and its above-average risk projects have a WACC of 12%.  Which of the following projects (A, B, and C) should the company accept? Project B, which is of below-average risk and has a return of 8.5%. Project C, which is of above-average risk and has a return of 11%. Project A, which is of average risk and has a return of 9%. None of the projects should be accepted. All of the projects should be accepted.                             
           Project B, which is of below-average risk and has a return of 8.5%.                             
           Project C, which is of above-average risk and has a return of 11%.                             
           Project A, which is of average risk and has a return of 9%.                             
           None of the projects should be accepted.                             
           All of the projects should be accepted.

Explanation / Answer

Project B, which is of below-average risk and has a return of 8.5%.