We are evaluating a project that costs $670,000, has a five-year life, and has n
ID: 2727593 • Letter: W
Question
We are evaluating a project that costs $670,000, has a five-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 59,000 units per year. Price per unit is $44, variable cost per unit is $24, and fixed costs are $760,000 per year. The tax rate is 35 percent, and we require a return of 18 percent on this project. Suppose the projections given for price, quantity, variable costs, and fixed costs are all accurate to within ±10 percent. I need the best case & worst case scenario for NPV.
Explanation / Answer
Calculation of best case NPV:
Year 0
Year 1
Year 2
Year 3
Year 4
Year 5
Sales (59000 units *110% ) *($44*110%)
$ 3,141,160.00
$ 3,141,160.00
$ 3,141,160.00
$ 3,141,160.00
$ 3,141,160.00
Less: Variable costs (59000 units *110% ) *($24*90%)
$ (1,401,840.00)
$ (1,401,840.00)
$ (1,401,840.00)
$ (1,401,840.00)
$ (1,401,840.00)
Less: Fixed Costs (760000*90%)
$ (684,000.00)
$ (684,000.00)
$ (684,000.00)
$ (684,000.00)
$ (684,000.00)
Less: Depreciation (670000-0) / 5)
$ (134,000.00)
$ (134,000.00)
$ (134,000.00)
$ (134,000.00)
$ (134,000.00)
Profit Before tax
$ 921,320.00
$ 921,320.00
$ 921,320.00
$ 921,320.00
$ 921,320.00
Less: Tax = Profit before tax * 35%
$ (322,462.00)
$ (322,462.00)
$ (322,462.00)
$ (322,462.00)
$ (322,462.00)
Profit after tax
$ 598,858.00
$ 598,858.00
$ 598,858.00
$ 598,858.00
$ 598,858.00
Add: Depreciation
$ 134,000.00
$ 134,000.00
$ 134,000.00
$ 134,000.00
$ 134,000.00
Cash Flows after tax
$ 732,858.00
$ 732,858.00
$ 732,858.00
$ 732,858.00
$ 732,858.00
Cost of Project
$ (670,000.00)
Net cash Flows (CF)
$ (670,000.00)
$ 732,858.00
$ 732,858.00
$ 732,858.00
$ 732,858.00
$ 732,858.00
PVF (18%)
1.00000
0.84746
0.71818
0.60863
0.51579
0.43711
1/(1+18%)^0
1/(1+18%)^1
1/(1+18%)^2
1/(1+18%)^3
1/(1+18%)^4
1/(1+18%)^5
PV = CF * PVF
$ (670,000.00)
$ 621,066.10
$ 526,327.20
$ 446,040.00
$ 378,000.00
$ 320,338.99
NPV = Sum of PV =
$ 1,621,772.30
Calculation of Worst case NPV:
Year 0
Year 1
Year 2
Year 3
Year 4
Year 5
Sales (59000 units *90% ) *($44*90%)
$ 2,102,760.00
$ 2,102,760.00
$ 2,102,760.00
$ 2,102,760.00
$ 2,102,760.00
Less: Variable costs (59000 units *90% ) *($24*110%)
$ (1,401,840.00)
$ (1,401,840.00)
$ (1,401,840.00)
$ (1,401,840.00)
$ (1,401,840.00)
Less: Fixed Costs (760000*110%)
$ (836,000.00)
$ (836,000.00)
$ (836,000.00)
$ (836,000.00)
$ (836,000.00)
Less: Depreciation (670000-0) / 5)
$ (134,000.00)
$ (134,000.00)
$ (134,000.00)
$ (134,000.00)
$ (134,000.00)
Profit Before tax
$ (269,080.00)
$ (269,080.00)
$ (269,080.00)
$ (269,080.00)
$ (269,080.00)
Less: Tax = Profit before tax * 35%
$ 94,178.00
$ 94,178.00
$ 94,178.00
$ 94,178.00
$ 94,178.00
Profit after tax
$ (174,902.00)
$ (174,902.00)
$ (174,902.00)
$ (174,902.00)
$ (174,902.00)
Add: Depreciation
$ 134,000.00
$ 134,000.00
$ 134,000.00
$ 134,000.00
$ 134,000.00
Cash Flows after tax
$ (40,902.00)
$ (40,902.00)
$ (40,902.00)
$ (40,902.00)
$ (40,902.00)
Cost of Project
$ (670,000.00)
Net cash Flows (CF)
$ (670,000.00)
$ (40,902.00)
$ (40,902.00)
$ (40,902.00)
$ (40,902.00)
$ (40,902.00)
PVF (18%)
1.00000
0.84746
0.71818
0.60863
0.51579
0.43711
1/(1+18%)^0
1/(1+18%)^1
1/(1+18%)^2
1/(1+18%)^3
1/(1+18%)^4
1/(1+18%)^5
PV = CF * PVF
$ (670,000.00)
$ (34,662.71)
$ (29,375.18)
$ (24,894.22)
$ (21,096.80)
$ (17,878.64)
NPV = Sum of PV =
$ (797,907.55)
Calculation of best case NPV:
Year 0
Year 1
Year 2
Year 3
Year 4
Year 5
Sales (59000 units *110% ) *($44*110%)
$ 3,141,160.00
$ 3,141,160.00
$ 3,141,160.00
$ 3,141,160.00
$ 3,141,160.00
Less: Variable costs (59000 units *110% ) *($24*90%)
$ (1,401,840.00)
$ (1,401,840.00)
$ (1,401,840.00)
$ (1,401,840.00)
$ (1,401,840.00)
Less: Fixed Costs (760000*90%)
$ (684,000.00)
$ (684,000.00)
$ (684,000.00)
$ (684,000.00)
$ (684,000.00)
Less: Depreciation (670000-0) / 5)
$ (134,000.00)
$ (134,000.00)
$ (134,000.00)
$ (134,000.00)
$ (134,000.00)
Profit Before tax
$ 921,320.00
$ 921,320.00
$ 921,320.00
$ 921,320.00
$ 921,320.00
Less: Tax = Profit before tax * 35%
$ (322,462.00)
$ (322,462.00)
$ (322,462.00)
$ (322,462.00)
$ (322,462.00)
Profit after tax
$ 598,858.00
$ 598,858.00
$ 598,858.00
$ 598,858.00
$ 598,858.00
Add: Depreciation
$ 134,000.00
$ 134,000.00
$ 134,000.00
$ 134,000.00
$ 134,000.00
Cash Flows after tax
$ 732,858.00
$ 732,858.00
$ 732,858.00
$ 732,858.00
$ 732,858.00
Cost of Project
$ (670,000.00)
Net cash Flows (CF)
$ (670,000.00)
$ 732,858.00
$ 732,858.00
$ 732,858.00
$ 732,858.00
$ 732,858.00
PVF (18%)
1.00000
0.84746
0.71818
0.60863
0.51579
0.43711
1/(1+18%)^0
1/(1+18%)^1
1/(1+18%)^2
1/(1+18%)^3
1/(1+18%)^4
1/(1+18%)^5
PV = CF * PVF
$ (670,000.00)
$ 621,066.10
$ 526,327.20
$ 446,040.00
$ 378,000.00
$ 320,338.99
NPV = Sum of PV =
$ 1,621,772.30
Calculation of Worst case NPV:
Year 0
Year 1
Year 2
Year 3
Year 4
Year 5
Sales (59000 units *90% ) *($44*90%)
$ 2,102,760.00
$ 2,102,760.00
$ 2,102,760.00
$ 2,102,760.00
$ 2,102,760.00
Less: Variable costs (59000 units *90% ) *($24*110%)
$ (1,401,840.00)
$ (1,401,840.00)
$ (1,401,840.00)
$ (1,401,840.00)
$ (1,401,840.00)
Less: Fixed Costs (760000*110%)
$ (836,000.00)
$ (836,000.00)
$ (836,000.00)
$ (836,000.00)
$ (836,000.00)
Less: Depreciation (670000-0) / 5)
$ (134,000.00)
$ (134,000.00)
$ (134,000.00)
$ (134,000.00)
$ (134,000.00)
Profit Before tax
$ (269,080.00)
$ (269,080.00)
$ (269,080.00)
$ (269,080.00)
$ (269,080.00)
Less: Tax = Profit before tax * 35%
$ 94,178.00
$ 94,178.00
$ 94,178.00
$ 94,178.00
$ 94,178.00
Profit after tax
$ (174,902.00)
$ (174,902.00)
$ (174,902.00)
$ (174,902.00)
$ (174,902.00)
Add: Depreciation
$ 134,000.00
$ 134,000.00
$ 134,000.00
$ 134,000.00
$ 134,000.00
Cash Flows after tax
$ (40,902.00)
$ (40,902.00)
$ (40,902.00)
$ (40,902.00)
$ (40,902.00)
Cost of Project
$ (670,000.00)
Net cash Flows (CF)
$ (670,000.00)
$ (40,902.00)
$ (40,902.00)
$ (40,902.00)
$ (40,902.00)
$ (40,902.00)
PVF (18%)
1.00000
0.84746
0.71818
0.60863
0.51579
0.43711
1/(1+18%)^0
1/(1+18%)^1
1/(1+18%)^2
1/(1+18%)^3
1/(1+18%)^4
1/(1+18%)^5
PV = CF * PVF
$ (670,000.00)
$ (34,662.71)
$ (29,375.18)
$ (24,894.22)
$ (21,096.80)
$ (17,878.64)
NPV = Sum of PV =
$ (797,907.55)
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.