Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

1. Cummings Products Company\'s cost of capital is 15% and the company is consid

ID: 2708151 • Letter: 1

Question

1.     Cummings Products Company's cost of capital is 15% and the company is considering two mutually exclusive projects. The projects' expected cash flows are as follows:

                

0

1

2

3

4

5

6

Project A

-550

160

160

160

160

160

160

Project B

-875

450

350

250

150

50

0

a.     What are the two projects

       

                

         

0

         

1

         

2

         

3

         

4

         

5

         

6

         

Project A

         

-550

         

160

         

160

         

160

         

160

         

160

         

160

         

Project B

         

-875

         

450

         

350

         

250

         

150

         

50

         

0

        Cummings Products Company's cost of capital is 15% and the company is considering two mutually exclusive projects. The projects' expected cash flows are as follows: What are the wo projects' payback periods? What are the two projects' IRRs? What are the two projects' NPVs? Which project should you choose?

Explanation / Answer

Hi,


Please find the answer as follows:


Part A:


Payback Period = Initial Investment/Annual Cash Inflows


Project A = 550/160 = 3.4375 or 3.44 Years


Project B = Out of 875 worth of initial investment 450 (Year 1) + 350 (Year 2) = 800 will get recovered in the first 2 Years. Remaining 75 will get recovered between Year 3 and Year 4


Payback Period = 2 + 75/250 = 2.3 Years


Part B:


Project A:


To calculate IRR, you need to put the value of NPV as 0 and solve for IRR as follows:


NPV = 0 = -550 + 160/(1+r)^1 + 160/(1+r)^2 + 160/(1+r)^3 + 160/(1+r)^4 + 160/(1+r)^5 + 160/(1+r)^6 = 18.68% or 18.68%


IRR = 16.20%


Project B:


To calculate IRR, you need to put the value of NPV as 0 and solve for IRR as follows:


NPV = 0 = -875 + 450/(1+r)^1 + 350/(1+r)^2 + 250/(1+r)^3 + 150/(1+r)^4 + 50/(1+r)^5 + 0/(1+r)^6 = 18.62%


IRR = 18.62%


Part C:


Project A = -550 + 160/(1+.15)^1 + 160/(1+.15)^2 + 160/(1+.15)^3 + 160/(1+.15)^4 + 160/(1+.15^5 + 160/(1+.15)^6 = 55.52


Project B = -875 + 450/(1+.15)^1 + 350/(1+.15)^2 + 250/(1+.15)^3 + 150/(1+.15)^4 + 50/(1+.15)^5 + 0/(1+.15)^6 = 55.96



Part D:


Project B should be selected.


Thanks.