ACS Industries is considering a project with an initial cost of $6.2 million. Th

ID: 2705592 • Letter: A

Question

ACS Industries is considering a project with an initial cost of $6.2 million. The project will produce cash inflows of $1.8 million a year for five years. The firm uses the subjective approach to assign discount rates to projects. For this project, the subjective adjustment is +2%. The firm has a pre-tax cost of debt of 6.7% and a cost of equity of 9.4%. The debt-equity ratio is 0.6 and the tax rate is 35%. What is the net present value of the project? Answer a. $742,067 b. $811,006 c. $733,333 d. $790,909 e. $710,053 ACS Industries is considering a project with an initial cost of $6.2 million. The project will produce cash inflows of $1.8 million a year for five years. The firm uses the subjective approach to assign discount rates to projects. For this project, the subjective adjustment is +2%. The firm has a pre-tax cost of debt of 6.7% and a cost of equity of 9.4%. The debt-equity ratio is 0.6 and the tax rate is 35%. What is the net present value of the project? ACS Industries is considering a project with an initial cost of $6.2 million. The project will produce cash inflows of $1.8 million a year for five years. The firm uses the subjective approach to assign discount rates to projects. For this project, the subjective adjustment is +2%. The firm has a pre-tax cost of debt of 6.7% and a cost of equity of 9.4%. The debt-equity ratio is 0.6 and the tax rate is 35%. What is the net present value of the project? $742,067 $811,006 $733,333 $790,909 $710,053 a. $742,067 b. $811,006 c. $733,333 d. $790,909 e. $710,053

Explanation / Answer

c. $733,333

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote