Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

We have discussed at length the Earned Value Management process. I am sure all o

ID: 2670762 • Letter: W

Question

We have discussed at length the Earned Value Management process. I am sure all of you have used the traditional process of assessing projects where we compare actual dollars spent to the amount we had planned to spend. This was quick and easy, but it has its shortcomings, and the Earned Value Management process is said to be better.

(a) Why is this traditional approach different from using earned value when assessing project performance?

(b) What are some of the basic requirements for the project plan in order for EVM to be able to work?

Explanation / Answer

A- Earned Value measures true cost performance while the traditional process measures cost in isolation of work progress. B- A planned value of the work that has been scheduled The actual value of the work that has been accomplished The actual costs incurred in accomplishing the work that has been scheduled

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote