Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Suppose that a mining operation has spent $8 million developing an ore deposit i

ID: 2649867 • Letter: S

Question

Suppose that a mining operation has spent $8 million developing an ore deposit in South America. Current expectations are that the deposit will require 2 years of development and will result in a realizable cash flow of $10 million at that time. The company engineer has discovered a new way of extracting the ore in only 1 year, but the procedure would necessitate an immediate outlay of $1 million.

Required:

Compute the IRR for the new outlay. (Note: There are two solutions! One is 787%. Find the other one.)

Based on your answer to (a), use the IRR criterion to determine if the company should make the outlay. Assume the market interest rate is 15% on 1- and 2-year bonds.

Explanation / Answer

Answer

a) Compute the IRR for the new outlay

A mining operation has spent $8 million developing an ore deposit in South America.

Current expectations are that the deposit will require 2 years of development and It will result in a realizable cash flow of $10 million at that time. So there will be inflow of $ 10 million at end of year 2.

The company engineer has discovered a new way of extracting the ore in only 1 year, but the procedure would necessitate an immediate outlay of $1 million.

So the company will receive inflow of $ 10 million at the end of year 1 provided it spends immediately $1 million. So total outflow at initial year 0 will be $ 9 million (8+1)

Now, Internal rate of return is discount rate makes the net present value of all cash flows from a particular project equal to zero.

We have to find out IRR by trail and error method by assuming different discount rates.

Suppose discount rate is 11.11%

                                                                         (Figures in millions)

year

Cash flow

Disc rate - 11.11%

Present value

A

B

A*B

0

-9

1

-9

1

10

0.90

9

IRR

11.11%

NPV

0

Answer : So IRR for new outlay is 11.11%

b)

Based on your answer to (a), use the IRR criterion to determine if the company should make the outlay. Assume the market interest rate is 15% on 1- and 2-year bonds.

If Company spends additional $ 1 million then IRR will be 11.11% as per answer (a)

If Company does not spend additional $ 1 million then IRR will be as per shown table below.

Suppose discount rate is 11.80%

      (Figures in millions)

year

Cash flow

0

-8

1

0

2

10

IRR

11.80%

Answer : So IRR as per answer a) is 11.11% and without additional outlay is 11.80% (in 2 years time) which is lower than market interest rate of 15% on 1- and 2-year bonds.

So company should not make outlay.

year

Cash flow

Disc rate - 11.11%

Present value

A

B

A*B

0

-9

1

-9

1

10

0.90

9

IRR

11.11%

NPV

0

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote