A B C D NPV $1,793,180 $1,732,583 $2,377,297 $1,640,093 IRR 18.03% 12.93% 15.47%
ID: 2621361 • Letter: A
Question
A
B
C
D
NPV
$1,793,180
$1,732,583
$2,377,297
$1,640,093
IRR
18.03%
12.93%
15.47%
13.03%
MIRR
15.48%
11.50%
12.11%
11.64%
Risk High Average Low Average
I/ Y 12.03% 9.03% 6.53% 9.03
1. Which of the projects are unacceptable and why?
2. Rank the projects that are acceptable, according to Mark
A
B
C
D
NPV
$1,793,180
$1,732,583
$2,377,297
$1,640,093
IRR
18.03%
12.93%
15.47%
13.03%
MIRR
15.48%
11.50%
12.11%
11.64%
Explanation / Answer
a) all projects are acceptable because every project has positive NPV
b) C > A >B >D
c) project C because it has highest NPV and other projects are not rejected because they are also having positive NPV