Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Note : the Answer should be computerized on word document and pasted in the answ

ID: 2601373 • Letter: N

Question

Note : the Answer should be computerized on word document and pasted in the answer slot

The business carried out some calculations on set up and the following information relating to their main product was produced Sales Revenue Direct labour (1 hour) Direct materials (1kg) Fixed overheads Standard profit 62 (22) (20) (14) The budgeted output for last month was 1,000 units of this product. Actual output was 1,100 units which were sold for £69,900. The actual production costs were Direct labour (1075 hours) Direct materials (1175 kg) Fixed overheads 24,420 23,260 6.400 There were no inventories at the start or the end of the month. You are required to calculate the variances for the month from the available information, and use them to reconcile the budgeted and actual profit figures. You should produce a document that identifies and explains the variances and reconciles the actual and budgeted profit figures. You should identify further information required that would help to further explain variances

Explanation / Answer

Direct matelial quantity variance =(Standard quantity-Actual quantity)Standard price

=(1000-1175)$20

=3500U

Direct material price variance = (Standard price-Actual price Actual) quantity

= ($20-$19.80)1,175

=240F

Direct labour efficiency variance= (Standard hours-Actual hours)Standard rate

=(1,000-1,075)$22

=1,650U

Direct labour rate variance = (Standard rate-Actual rate) Actual hours

=(22-$22.72)1,075

=770U

Fixed overhead expenditure valiance

= (6,000-6,400)

=400U

Sales Quantity variance

=(1100-1000)62

=6200F

Sales Price variance

=(63.55-62)1100

=1700F

Particulars

Amount ($)

Sales

69900

Particulars

Amount ($)

Less=

Direct material price variance

-3500

Direct labour

24420

Direct material quantity variance

240

Direct meterial

23260

Direct labour rate variance

-1650

Fixed overhead

6400

Direct labour efficiency variance

-770

Total

-54080

Fixed overhead expenditure variance

-400

Sales quantity variance

6200

Actual margin

15820

Sales price variance

1700

Budgeted margin

14000

Total variance

1820

Variance

1820

Particulars

Amount ($)

Sales

69900

Particulars

Amount ($)

Less=

Direct material price variance

-3500

Direct labour

24420

Direct material quantity variance

240

Direct meterial

23260

Direct labour rate variance

-1650

Fixed overhead

6400

Direct labour efficiency variance

-770

Total

-54080

Fixed overhead expenditure variance

-400

Sales quantity variance

6200

Actual margin

15820

Sales price variance

1700

Budgeted margin

14000

Total variance

1820

Variance

1820

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote