Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

At times, Holiday takes on long term projects for theme parks. During 2016, Holi

ID: 2599956 • Letter: A

Question

At times, Holiday takes on long term projects for theme parks. During 2016, Holiday took on 4-year, long term project for Christmas Land, a destination theme park in Fargo, North Dakota. The total estimated cost of the project was $8,000,000 and the contract was for $9,850,000. The detail of the project to date is as follows: Note: the 2016 entries are already reflected in the 2016 trial balance but none of the 2017 entries have been recorded.

2016:   Costs Incurred                         $3,500,000

            Estimated Costs to Complete $6,500,000

            Billings                                    $2,800,000

            Customer Receipts                 $1,980,000

2017:   Costs Incurred                         $2,750,000

            Estimated Costs to Complete $3,875,000

            Billings                                                $2,010,000

prepare appropriate analysis and journal entries

Explanation / Answer

Journal entries for the year 2017 (Amount in $)

The total cost in 2016 = Cost incurred+Total estimated costs = $3,500,000+$6,500,000 = $10,000,000

Contract Price = $9,850,000

As the contract price is less than the total cost, Holiday should provide the amount of $150,000 ($10,000,000-$9,850,000) as reserve for loss on contract.

In 2017, The total cost = Cost incurred for 2016 and 2017+Estimated cost

= $3,500,000+$2,750,000+$3,875,000 = $10,125,000

The contract price is less than total cost by $275,000 ($10,125,000-$9,850,000). the excess reserve fof loss on contract is required for $125,000 ($275,000-$150,000) for 2017.

Account Title Debit Credit Work in progress 2,750,000 Accounts Payable 2,750,000 (To record the cost incurred) Accounts Receivable 2,010,000 Billings 2,010,000 (To record the amount billed)