Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

VARIANCE ANALYSIS IN A PROCESS-COSTING SETTING Problem 9-36 CHAPTER 6 REQUIRED),

ID: 2598430 • Letter: V

Question

VARIANCE ANALYSIS IN A PROCESS-COSTING SETTING Problem 9-36 CHAPTER 6 REQUIRED), SERVICE FIRM Aspen Medical Laboratory performs comprehensive blood tests for physicians and clinics throughout the Southwest. Aspen uses a standard process-costing system for its co hensive blood work. Skilled technicians perform the blood tests. Because Aspen uses a standard costing system, equivalent units are calculated using the FIFO mcthod. The standard cost sheet for the blood test follows (these standards were used throughout the calendar year): mpre-

Explanation / Answer

1. Standard Costing system is used to calculate the variances in the materials, labor & overheads for comparing the budgeted results with actual results. Such variances are implemented on the basis of the actual output prodduced during the period. FIFO method is used to calculate the equivalent units produced during this period so that actual result can be calculated on the basis of such units produced and sold.

2. Calculation of Cost of goods Sold (Actual basis not budgeted)

Calculation of Equivalent tests completed during the period

Equivalent units

Period

Units

Completed

Equivalent units

Beginning WIP

1,250

40% (Completed this year)

1250 x 40% = 500 units

Tests Started

25,000

100% of (25000-2500)

22,500

Ending WIP

2,500

40%

2,500 x 40% = 1,000

Equivalent tests completed

24,000 tests

Note: Being FIFO method ending WIP is including tests started during this year only.

Cost of Goods Sold / Tests Completed = Materials + Labor cost + Variable overheads

= (102,000 x $4.25) + (47,000 x 19) + 144,000 = $1,470,500

Cost of goods sold per unit = $1,470,500 / 24,000 tests = $61.2708 per test

3. Calculation of Variances

a. Material Price Variance = (Standard Rate - Actual Rate) x Materials Purchased

Standard Rate = $4.50

Actual Rate = $4.25

Material Price Variance = (4.50 - 4.25) x 102,000 = $25,500 Favorable

b. Material Quantity Variance = (Standard Quantity for actual output - Actual Quantity) x Standard Rate

Standard Quantity for actual output = 24,000 tests x 4 oz = 96,000 oz.

Actual Quantity used = 102,000 oz

Material Quantity Variance = (96,000 - 102,000) x 4.50 = $27,000 Unfavorable.

c. Labor Rate Variance = (Standard Rate per hour - Actual Rate) x Actual hours worked

= (18 - 19) x 47,000 = $47,000 Unfavorable

d. Labor efficiency variance = (Standard hours for actual output - Actual hours) x Standard Rate per hour

Standard hours = 24,000 tests x 2 hours = 48,000 hours

Actual Hours = 47,000

Labor efficiency variance = (48,000 - 47,000) x 18 = $18,000 Favorable

Period

Units

Completed

Equivalent units

Beginning WIP

1,250

40% (Completed this year)

1250 x 40% = 500 units

Tests Started

25,000

100% of (25000-2500)

22,500

Ending WIP

2,500

40%

2,500 x 40% = 1,000

Equivalent tests completed

24,000 tests