Slide 5 chapter 09 Performance Measurement and Responsibililty Accounting Compute cycle time and cycle elficienoy, and explain their importance to production management points Knowledge Check 02 Select the best answer to the question Question 1ot1 The sailboat Company makes sailboats. To make one svat it takes 2 days to move all the wood into the production factory, 5 days to cut, assembie, and glue the wood togetner to make the boat. 2 days for the glue to dry and 1 day to take the boat to the lake to see whether it loats what is the cycle emciency of the Sailboat Company? 5 days 4 days 40% 50%Explanation / Answer
1.
Move time = wood into factory = 2 days
Processing time = assemble work = 5 days
Queue time = dry work = 2 days
Inspection timing = Test to float = 1 days
Cycle time = Processing time + Inspection timing + Move time + Queue time
= 5 + 1 + 2 + 2
= 10 days
Cycle efficiency = (Processing time / Cycle time) × 100
= (5 / 10) × 100
= 50%
Answer: the last option
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.