Question 49 1 points Save An Dehner Corporation uses a job-order costing system predetermined overhead rate based on direct labor-hours. The company based its predetermined overhoad rate for tetal direet 1abor-hours Total ixed sanufacturing overhead cost Varlable sanafacturing overhead per direct labor- 196,000 3.00 Recently, Job P951 was completed with the following characteristios usber of unite is the ob Total direet labor-our Direct materiale 100 755 “.saa The predetermined overhead rate is closest to: 2.40 per direct labor hour $3.00 per direct labor-hour $8.40 per direct labor-hour $5.40 per drect labor-hourExplanation / Answer
Total overhead=Fixed overhead+Variable overhead
=96000+(40000*3)=$216000
Hence predetermined overhead rate=($216000/40,000)
=$5.4/direct labor hour.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.