Question

ter 12 Quiz 6 Help Save&Exit; Sub Two alternatives, code-named X and Y, are under consideration at Guyer Corporation. Costs associated with the alternatives are listed below. Alternative Alternative Materials costs Processing costs Equipment rental Occupancy costs 41,000 $45,000 $17,000 $16,000 $59,000 $45,000 $17,000 $24,000 Are the materials costs and processing costs relevant in the choice between alternatives X and Y? Multiple Choice Neither materials costs nor processing costs are relevant Only processing costs are relevant Only Prev 5 of 10 ::: Next >

Explanation / Answer

In the above question material cost is relevant because material cost is differ in both situation but processing cost is not relevant because processing cost is same is both alternative