Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

PLEASE HELP! I have tried everything and can\'t figure it out! Cost of Productio

ID: 2566306 • Letter: P

Question

PLEASE HELP! I have tried everything and can't figure it out!

Cost of Production Report The Cutting Department of Tangu Carpet Company provides the following data for December 2014. Assume that all materials are added at the beginning of the process. work in process, December 1, 14,400 units, 55% completed $161,136 $115,200 45,936 $161,136 "Direct materials (14,400 × $8.00) conversion (14,400 × 55% × $5.80) Materials added during December from Weaving Department, 221,600 units Direct labor for December Factory overhead for December Goods finished during December (includes goods in process, December 1), 224,200 units work in process, December 31, 11,800 units, 30% completed $1,783,880 563,838 689,136 l@ a. Prepare a cost of production report for the Cutting Department. If an amount is zero or a blank, enter in"O". For the cost per equivalent unit computations, round your answers to two Hide Hintis) decimal places.

Explanation / Answer

Solution:

I am providing here the correct answers related to following:

Equivalent Units for Conversion

Equivalent Units

Whole Unit

Direct Material

Conversion

Inventory in process, Dec 1

14400

It is correct in the question

6480

Started and completed in December

209800

209800

Transferred to finished goods in December

224200

216280

Inventory in Process, Dec 31

11800

3540

Total units to be assigned cost

236000

219820

Cost per Equivalent Unit for Conversion

Cost per Equivalent Unit:

Direct Material

Conversion

Total costs for December in Cutting Dept.

It is correct in the question

$1,252,974

Total Equivalent Units

219820

Cost per Equivalent unit

$5.70

Cost assigned and allocated to complete and partially completed units

Cost Assigned to production:

Direct Material

Conversion Costs

Total Cost

Inventory in process, Dec 1

$0

Costs incurred in December

$3,036,854

Total costs accounted for by the cutting department

$3,036,854

Cost allocated to completely and partially completed units:

Inventory in process, Dec 1 balance

$161,136

To complete inventory in process Dec 1

$0

$36,936

(6480*5.7)

$36,936

Cost of completed Dec 1 work in process

$198,072

Started and Completed in December

$1,688,890

$1,195,860

(209800*5.7)

$2,884,750

Transferred to finished goods in December

$3,082,822

Inventory in process, December 31

$94,990

$20,178

(3540*5.7)

$115,168

Total costs assigned by the cutting department

$3,197,990

Change in Conversion Cost per equivalent Unit = (5.80 – 5.70) = $0.10 Decrease

Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you

Equivalent Units

Whole Unit

Direct Material

Conversion

Inventory in process, Dec 1

14400

It is correct in the question

6480

Started and completed in December

209800

209800

Transferred to finished goods in December

224200

216280

Inventory in Process, Dec 31

11800

3540

Total units to be assigned cost

236000

219820

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote