You have been given the following information about the production of Usher Co., and are asked to provide the plant manager with information for a meeting with the vice president of operations.


The following is a variance report for the most recent period of operations.

Variances

Costs

Total Standard Cost

Price

Quantity

What was the actual cost per pound of raw materials? (Round answer to 2 decimal places, e.g. 1.25.)

Standard Cost Card Direct materials (9 pounds at $4 per pound) $36.00 Direct labor (0.80 hours at $7) 5.60 Variable overhead (0.80 hours at $3 per hour) 2.40 Fixed overhead (0.80 hours at $8 per hour) 6.40 $50.40

Explanation / Answer

Calculate actual cost per pound :

Direct material rate variance = (Standard rate-actual rate)actual quantity

5770 = (4X-410430)

-4X = -416200

X(Actual Quantity) = 104050

Actual cost per pound = 410430/104050 = 3.94 per pound