You have been given the following information about the production of Usher Co.,
ID: 2557894 • Letter: Y
Question
You have been given the following information about the production of Usher Co., and are asked to provide the plant manager with information for a meeting with the vice president of operations.
The following is a variance report for the most recent period of operations.
Variances
Costs
Total Standard Cost
Price
Quantity
What was the actual cost per pound of raw materials? (Round answer to 2 decimal places, e.g. 1.25.)
Standard Cost Card Direct materials (9 pounds at $4 per pound) $36.00 Direct labor (0.80 hours at $7) 5.60 Variable overhead (0.80 hours at $3 per hour) 2.40 Fixed overhead (0.80 hours at $8 per hour) 6.40 $50.40Explanation / Answer
Calculate actual cost per pound :
Direct material rate variance = (Standard rate-actual rate)actual quantity
5770 = (4X-410430)
-4X = -416200
X(Actual Quantity) = 104050
Actual cost per pound = 410430/104050 = 3.94 per pound
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.