You have been given the following information about the production of Usher Co.,

ID: 2508498 • Letter: Y

Question

You have been given the following information about the production of Usher Co., and are asked to provide the plant manager with information for a meeting with the vice president of operations.


The following is a variance report for the most recent period of operations.

Variances

Costs

Total Standard Cost

Price

Quantity

Direct labor

U

Standard Cost Card Direct materials (8 pounds at $5 per pound) $40.00 Direct labor (0.70 hours at $10) 7.00 Variable overhead (0.70 hours at $3 per hour) 2.10 Fixed overhead (0.70 hours at $7 per hour) 4.90 $54.00

Explanation / Answer

Calculate unit produced durin period :

Unit produced = Total standard cost/standard cost per unit = 410000/40 = 10250 units