Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

thanks again for any help on this You have been given the following list of vari

ID: 2557396 • Letter: T

Question

thanks again for any help on this

You have been given the following list of variances for the Pennadi Company Direct materials price variance Direct materials quantity variance Direct labour rate variance Direct labour efficiency variance Variable overhead spending variance Variable overhead efficiency variance Fixed overhead budget variance Fixed overhead volume variance $11,700 U 11,700 U 4,420 F 45,000 U 2,940 U 5,700 U 4,700 U 68,400 F You have also been given the following information Actual units produced Budgeted units of production (normal volume) Standard labour-hours for actual output Standard material units for actual output Actual direct labour costs Actual cost of direct materials 26,000 20,000 13,000 370,000 $235,580 $391,950 Overhead is applied using direct labour-hours. Variable overhead is applied at the rate of $10 per direct labour-hour. The materials purchase price was $0.670.(Attempt the following questions in the order listed.)

Explanation / Answer

Requirement 1

Actual cost of direct materials

391950

The material purchase price

0.67

Actual number of units purchased (391950/0.670)

585000

Requirement 2

Standard cost of actual number of units (585000 x 0.65)

380250

Standard price of direct materials

0.65

Requirement 3

391950

Requirement 4

380250

Requirement 5

370000 units

Requirement 6

Actual direct labour cost

235580

Less: Direct labour efficiency variance

45000

190580

Add: Direct labour rate variance

4420

195000

Thus, standard labour cost should have been

195000

Standard labour hour

13000

Since actual labour cost

235580

Actual labour hour worked (13000 x 235580 / 195000)

15705.33

Requirement 7

Direct materials

0.65

Standard materials units

370000

Standard production

20000

Materials per unit of output

18.5

12.025

Thus, standard labour cost should have been

195000

Standard labour hours

13000

Standard labour cost for each unit of output

9.75

Variable cost (0.65 x 10)

6.5

28.275

Requirement 8

Fixed overhead volume allocation (F)

68400

Less: Fixed overhead budget variance

4700

63700

Budgeted unit of production

20000

Actual unit of production

26000

Difference in production (26000 - 20000)

6000

Fixed overhead allocation (63700 /6000)

10.61667

Requirement 9

Number of units produced

26000

Fixed overhead allocation (63700 /6000)

10.61667

Actual fixed overhead cost

276033.3

Budgeted fixed costs

Actual fixed overhead cost

276033.3

Less: Favourable fixed overhead volume variance

68400

207633.3

Add: Unfavourable fixed overhead budget variance

4700

212333.3

Allocated fixed costs

Actual fixed overhead cost

276033.3

Number of units produced

26000

Allocated fixed costs (276033.3/26000)

10.61667

Requirement 10:

Allocated fixed costs (276033.3/26000)

10.61667

Actual fixed overhead cost

276033.3

Less: Budgeted fixed costs

212333.3

Over applied fixed overhead cost

63700

Budgeted fixed costs

1.3

Requirement 1

Actual cost of direct materials

391950

The material purchase price

0.67

Actual number of units purchased (391950/0.670)

585000

Requirement 2

Standard cost of actual number of units (585000 x 0.65)

380250

Standard price of direct materials

0.65

Requirement 3

391950

Requirement 4

380250

Requirement 5

370000 units

Requirement 6

Actual direct labour cost

235580

Less: Direct labour efficiency variance

45000

190580

Add: Direct labour rate variance

4420

195000

Thus, standard labour cost should have been

195000

Standard labour hour

13000

Since actual labour cost

235580

Actual labour hour worked (13000 x 235580 / 195000)

15705.33