Question
The auto repair shop of Quality Motor Company uses standards to control the labor time and labor cost in the shop. The standard labor cost for a motor tune-up is given below: Job Motor tune-up Standard Hours Standard Rate Standard Cost 1.80 $5.50 $9.90 The record showing the time spent in the shop last week on motor tune-ups has been misplaced. However, the shop supervisor recalls that 170 tune-ups were completed during the week, and the controller recalls the following variance data relating to tune-ups: Labor rate variance Labor $ 55 F $1.287 U spending variance hte Deiremine the number of actual labor-hours spent on tune aps durng the week 1. Determine the number of actual labor-hours spent on tune-ups during the week. Actual labor hours hours 2. Determine the actual hourly rate of pay for tune-ups last week. (Round your answer to 2 decimal places.) Actual hourly rate per hourExplanation / Answer
Labor efficiency variance=1287+55 = 1342U 1 Labor efficiency variance=SR*(AH-SH) 1342=5.50*(AH-170*1.8) 1342=5.50*(AH-170*1.8) 244=AH-306 AH = 550 Actual labor hours=550 hours 2 Labor rate variance=AH*(SR-AR) 55=550*(1.8-AR) 0.1=1.8-AR AR=$1.7 Actual hourly rate=$1.70 per hour
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.