Redel Inc. has the following results for the current period Budget Actual Fixed
ID: 2546248 • Letter: R
Question
Redel Inc. has the following results for the current period
Budget
Actual
Fixed Overhead
$ 153941
$ 158618
Units produced
6513
6109
Direct labour hours
13026
321193
Fixed overhead is applied at $12 per direct labour hour. Variable overhead is applied at $27.50 per DLH. The standard hours per unit are 2 direct labour hours. Actual variable overhead was $321193.
Which of the following amounts represents the fixed overhead budget variance? (a negative number implies an unfavourable variance)
Select one:
a. $-7325
b. $4677
c. $-4677
d. $7325
Redel Inc. has the following results for the current period
Budget
Actual
Fixed Overhead
$ 153941
$ 158618
Units produced
6513
6109
Direct labour hours
13026
321193
Fixed overhead is applied at $12 per direct labour hour. Variable overhead is applied at $27.50 per DLH. The standard hours per unit are 2 direct labour hours. Actual variable overhead was $321193.
Which of the following amounts represents the fixed overhead budget variance? (a negative number implies an unfavourable variance)
Explanation / Answer
Fixed overhead budget variance = Budgeted fixed overhead - Actual fixed overhead
Fixed overhead budget variance = $153,941 - $158,618
Fixed overhead budget variance = $-4,677
So, answer is c.$-4,677