Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Pad t * 100%- Weygandt, Financial & Managerial Accounting, 2e Cheater 17 Homewor

ID: 2545385 • Letter: P

Question

Pad t * 100%- Weygandt, Financial & Managerial Accounting, 2e Cheater 17 Homework Rosenthal Company manufactures bowling balls through two processes: Molding and Packaging. In the Molding Department, the urethane, rubber, pastics, and other materials are molded into bowing bans[n the Packagng Department, the bals are placed in cartons and sent to the inished goods warehouse. All materials are entered at the beginning of each process. Labor and manufacturing overhead are incurred unformly throughout each process. Production and cost data for the Molding Department during June 2017 are presented below beruse12.1 Exercise i Beginning work in process units Units started into production 22,660 2,060 Review Results by Stdy Ending work in process units s 203,940 5,208 6,184 is correct Prepare a schedule showing physical units of preduction. Physical units Units to be accounted for Work in process, June 1 Started into preduction 22660 Units accounted for process, June 30 Your answer is incomect. Try again, Determine the equivalent units of production for materials and conversion costs otal equwalent units Your answer is incomect. Try again Compute the unit costs of production. (Round unit costs to 2 decimal places, e.g. 225.)

Explanation / Answer

Prepare a schedule showing Physical units of production

$

Units to be accounted for

Work in process, june 1

0

Started into production

22660

Total units

22660

Units Accounted for

Completed and transferred out

20600

Ending work in process

2060

Total units

22660

Determine the equivalent units of production for materials and conversion costs

Materials

Conversion costs

Transferred out

20600

20600

work in process

(2060*100%)

2060

(2060*40%)

824

Total

22660

21424

Compute the unit cost of production

Unit Material cost:

Total Material cost/ Equivalent cost

203940/22660

9

Unit conversion cost:

Total conversion cost/Equivalent unit of conversion costs

8

[55208+116184]/21424

Materials

$9

Conversion cost

$8

Determine the cost to be assigned to the units transferred out and in process for june

Work in process

$

Transferred out [20600*$17]

350200

Materials [2060*$9]

18540

Conversion cost [824*$8]

6592

Total costs

375340

Prepare a production cost report for the molding department fo the month of june

Rosenthal company

Molding Department

Production cost report

For the month of june 30

Physical units

Materials

Conversion costs

Amount

Work in process

0

Started in production

20600

Total units

20600

Units accounted for

Transferred out

20600

20600

20600

Work in process

2060

2060

824

22660

22660

21424

Unit costs

Materials

Conversion cost

Total

Total costs

203940

171392

375332

Equivalent units

22660

21424

Unit costs

9

8

17

Cost to be accounted for

Work in process june 1

0

Started into production

375332

Total costs

375332

Cost reconciliation schedule

Cost Account for

Transferred out (20600*$17)

350200

Work in process june 1

Materials (2060*9)

18540

Conversion costs (824*8)

6592

25132

Total costs

375332

Prepare a schedule showing Physical units of production

$

Units to be accounted for

Work in process, june 1

0

Started into production

22660

Total units

22660

Units Accounted for

Completed and transferred out

20600

Ending work in process

2060

Total units

22660

Determine the equivalent units of production for materials and conversion costs

Materials

Conversion costs

Transferred out

20600

20600

work in process

(2060*100%)

2060

(2060*40%)

824

Total

22660

21424

Compute the unit cost of production

Unit Material cost:

Total Material cost/ Equivalent cost

203940/22660

9

Unit conversion cost:

Total conversion cost/Equivalent unit of conversion costs

8

[55208+116184]/21424

Materials

$9

Conversion cost

$8

Determine the cost to be assigned to the units transferred out and in process for june

Work in process

$

Transferred out [20600*$17]

350200

Materials [2060*$9]

18540

Conversion cost [824*$8]

6592

Total costs

375340

Prepare a production cost report for the molding department fo the month of june

Rosenthal company

Molding Department

Production cost report

For the month of june 30

Physical units

Materials

Conversion costs

Amount

Work in process

0

Started in production

20600

Total units

20600

Units accounted for

Transferred out

20600

20600

20600

Work in process

2060

2060

824

22660

22660

21424

Unit costs

Materials

Conversion cost

Total

Total costs

203940

171392

375332

Equivalent units

22660

21424

Unit costs

9

8

17

Cost to be accounted for

Work in process june 1

0

Started into production

375332

Total costs

375332

Cost reconciliation schedule

Cost Account for

Transferred out (20600*$17)

350200

Work in process june 1

Materials (2060*9)

18540

Conversion costs (824*8)

6592

25132

Total costs

375332