During the month of January, the materials requisitions and direct labor time ti
ID: 2538267 • Letter: D
Question
During the month of January, the materials requisitions and direct labor time tickets showed the following information:
Date Job Number Materials Used
1/1 George-1 $13,200
1/6 Builder-35 37,250
1/15 George-1 8,700
1/22 Stephen-63a 23,750
Date Job Number DL Hours
1/2 George-1 65
1/9 Builder-35 17
1/16 George-1 36
1/16 Stephen-63a 18
1/30 Stephen-63a 29
Compute the costs incurred for the month on each job. Use the DL average rate of $45 per hour and the overhead allocation rate of 150% of DL cost. Remember that the cost of any job is DM+DL+OH. Note that George-1 was started and completed, Builder-35 was started but not yet completed, and Stephen-63a was completed and shipped by the end of the month.
a. Job Stephen-63a, total costs =
b. The Stephen-63a job was a rush job, so the company will markup accordingly. If the company prices this job at 200% of cost, what will job Stephen-63a be sold for?
c. What is the balance in work in process inventory at the end of the month?
Explanation / Answer
Solution:
a. Job Stephen-63a Total Cost = $29,037.50
b. If stephen-63a job priced at 200% of cost then sale value of Stephen-63a = $29,037.50 *200% = $58,075
c. The builder-35 job was started in january but not yet completed, therefore cost of builder-35 incurred till date will be the balance in WIP inventory at the end of the month = $39,162.50
Computation of cost incurred for the month on each job Particulars George - 1 Builder - 35 Stephen - 63a Material used $21,900.00 $37,250.00 $23,750.00 Direct Labor hours 101 17 47 Direct labor average rate per hour $45.00 $45.00 $45.00 Direct Labor cost incurred (DL Hours * Average Rate) $4,545.00 $765.00 $2,115.00 Overhead Allocation (150% of direct labor cost) $6,817.50 $1,147.50 $3,172.50 Total Cost (Material + Direct Labor + Overhead) $33,262.50 $39,162.50 $29,037.50Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.