Amber Company produces iron table and chair sets. During October, Amber’s costs
ID: 2523842 • Letter: A
Question
Amber Company produces iron table and chair sets. During October, Amber’s costs were as follows:
Required:
1. Calculate the total cost of purchases for October.
Total Purchases=
2. Compute the direct materials price variance based on quantity purchased. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable.)
3. Calculate the direct materials quantity variance based on quantity used. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable.)
4. Compute the standard direct labor rate for October. (Round your answer to 2 decimal places.)
5. Compute the direct labor efficiency variance for October. (Round your intermediate calculation to 2 decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable.)
Actual purchase price $ 3.20 per lb. Actual direct labor rate $ 8.40 per hour Standard purchase price $ 3.00 per lb. Standard quantity for sets produced 1,060,000 lbs. Standard direct labor hours allowed 21,000 Actual quantity purchased in October 1,365,000 lbs. Actual direct labor hours 19,000 Actual quantity used in October 1,090,000 lbs. Direct labor rate variance $6,400 FRequired:
1. Calculate the total cost of purchases for October.
Total Purchases=
2. Compute the direct materials price variance based on quantity purchased. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable.)
Direct Materials Price Variance3. Calculate the direct materials quantity variance based on quantity used. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable.)
Material Quantity Variance4. Compute the standard direct labor rate for October. (Round your answer to 2 decimal places.)
Standard Direct Labor Rate5. Compute the direct labor efficiency variance for October. (Round your intermediate calculation to 2 decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable.)
Direct Labor Efficiency VarianceExplanation / Answer
1) Total purchase = 3.20*1365000 = 4368000
2) Material price variance = (3-3.20)*1365000 = 273000 U
3) Material quantity variance = (1060000-1090000)*3 = 90000 U
4) Labour rate variance = (Standard rate-actual rate)Actual hour
6400 = (X*19000-19000*8.40)
-19000X = -166000
X(standard rate) = 8.74
5) Direct labour efficiency variance = (21000-19000)*8.74 = 17474 F