Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

298 The Investment Decision 14 14. Castle Rock Medical Center expects Projects X

ID: 2522607 • Letter: 2

Question

298 The Investment Decision 14 14. Castle Rock Medical Center expects Projects X and Y to generate the follo ing cash flows: Givens (in thousands) Years 0 3 ($6,500) Initial investment Net operating cash flows for Project X Net operating cash flows for Project Y Discount rate for Part a Discount rate for Part b $5,000 $3,000 $2,000 $1,600 $1,000 $1,000 $1,600 $2,000 $3,000 $5,000 13% 8% a. Determine the NPV for both projects using a cost of capital of 13 percent. b. Determine the NPV for both projects using a cost of capital of 8 percent. c. At an 8 percent discount rate, which project should be accepted? At a 13 percent discount rate, which project should be accepted? Explain.

Explanation / Answer

1-

Project X

Project Y

year

cash flow

present value of cash flow = cash flow/(1+r)^n r= 13%

year

cash flow

present value of cash flow = cash flow/(1+r)^n r= 13%

0

-6500

-6500

0

-6500

-6500

1

5000

4424.779

1

1000

884.9558

2

3000

2349.44

2

1600

1253.035

3

2000

1386.1

3

2000

1386.1

4

1600

981.31

4

3000

1839.956

5

1000

542.7599

5

5000

2713.8

NPV

sum of present value of cash flow

3184.389

NPV

sum of present value of cash flow

1577.847

2-

Project X

Project Y

year

cash flow

present value of cash flow = cash flow/(1+r)^n r= 8%

year

cash flow

present value of cash flow = cash flow/(1+r)^n r= 8%

0

-6500

-6500

0

-6500

-6500

1

5000

4629.63

1

1000

925.9259

2

3000

2572.016

2

1600

1371.742

3

2000

1587.664

3

2000

1587.664

4

1600

1176.048

4

3000

2205.09

5

1000

680.5832

5

5000

3402.916

NPV

sum of present value of cash flow

4145.942

NPV

sum of present value of cash flow

2993.338

3-

At 13%

Project X should be selected as its NPV is greater than project B

at 8%

Project X should be selected as its NPV is greater than project B

1-

Project X

Project Y

year

cash flow

present value of cash flow = cash flow/(1+r)^n r= 13%

year

cash flow

present value of cash flow = cash flow/(1+r)^n r= 13%

0

-6500

-6500

0

-6500

-6500

1

5000

4424.779

1

1000

884.9558

2

3000

2349.44

2

1600

1253.035

3

2000

1386.1

3

2000

1386.1

4

1600

981.31

4

3000

1839.956

5

1000

542.7599

5

5000

2713.8

NPV

sum of present value of cash flow

3184.389

NPV

sum of present value of cash flow

1577.847

2-

Project X

Project Y

year

cash flow

present value of cash flow = cash flow/(1+r)^n r= 8%

year

cash flow

present value of cash flow = cash flow/(1+r)^n r= 8%

0

-6500

-6500

0

-6500

-6500

1

5000

4629.63

1

1000

925.9259

2

3000

2572.016

2

1600

1371.742

3

2000

1587.664

3

2000

1587.664

4

1600

1176.048

4

3000

2205.09

5

1000

680.5832

5

5000

3402.916

NPV

sum of present value of cash flow

4145.942

NPV

sum of present value of cash flow

2993.338

3-

At 13%

Project X should be selected as its NPV is greater than project B

at 8%

Project X should be selected as its NPV is greater than project B

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote