Question
OUEST?ONAi ICQ Questions : Which of these is not an input to the Control Procurement process? A. Agreements B. work performance data C. Change requests D. Work performance reports The types of contracts that can be used in a project are documented in the: A. Procurement management plan B. Request for Proposal (RFP) C. Procurement statement of work D. Work breakdown structure (WBS) 2- 3. The fixed price contract is advantageous to the buyer because it A. requires extremely well defined specifications 3. requires formal procedures for scope changes C. contractor assumes financial and technical risk D. has a known cost 4- Which of the following statements is not a Plan Procurement outputs? A. Procurement Management Plan. B. Source Selection Criteria C. Expert judgment. D. Independent Cost Estimates. 5- Which of the following statements is not accurate regarding time and material contracts. A. Used in an emergency to begin work immediately B. Used for small amount and shorter length of time. C. The buyer has a medium amount of cost risk. D. Can't be left open ended and may not be subject to a cost increase t buyer 6- Types of contract selection can be based upon: A. Overall degree of Cost &Schedule; Risk B. Extent of Price Competition C. Performance period D. All of the aboveExplanation / Answer
Answer = 1) Answer = Option C = Change Request Answer = 2) Answer = Option C = Procurement statement of work Answer = 3) Answer = Option D = Has a known Cost Answer = 4) Answer = Option C = Expert Jusdgment
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.