The auto repair shop of Quality Motor Company uses standards to control the labo
ID: 2520442 • Letter: T
Question
The auto repair shop of Quality Motor Company uses standards to control the labor time and labor cost in the shop. The standard labor cost for a motor tune-up is given below: Standard Hours 1.50 Standard Rate $6.00 Standard Cost $9.00 Motor tune-up The record showing the time spent in the shop last week on motor tune-ups has been misplaced. However, the shop supervisor recalls that 150 tune-ups were completed during the week, and the controller recalls the following variance data relating to tune ups: Labor rate variance Labor spending variance 1,000 U $ 470 F Required: 1. Determine the number of actual labor-hours spent on tune-ups during the week. 2. Determine the actual hourly rate of pay for tune-ups last week. (Round your answer to 2 decimal places.) 1. Actual labor hours hours Actual hourly rate per hour 2.Explanation / Answer
Labour efficiency variance = 1000+470 = 1470 U
Labour efficiency variance = (Standard hour-actual hour)Standard rate
-1470 = (150*1.5*6-6X)
-1470 = 1350-6X
6X = 2820
X(actual hour) = 470 hour
Labour rate variance = (Standard rate-actual rate)actual hour
470 = (6*470-470X)
470 = 2820-470X
470X = 2350
X(actual hourly rate) = 5 per hour
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.