The following table shows the probability distribution of the number of days (x)

ID: 2505869 • Letter: T

Question

The following table shows the probability distribution of the   number of days (x) to complete a certain type of construction project by a   contractor.










x f(x)







1 0.05







2 0.20







3 0.35







4 0.30







5 0.10
















3 The probability that it   will take less than 3 days to complete a randomly selected project is ______. a 0.60







b 0.45







c 0.35







d 0.25

















4 The standard deviation of   the days to complete a project is _______.   (Rounded to 2 decimal points.) a 1.03







b 1.24







c 1.35







d 1.41

















5 The   contractor's project cost is made up of a fixed cost of $20,000, plus $2,000   for each day taken to complete the project.   Expected value of total project cost is.
a $25,300







b $26,400







c $27,500







d $28,600

















6 In the previous question   the standard deviation of total project cost is:

a $22,060







b $22,828







c $2,060







d $2,828

















7 If you toss a balanced   coin 20 times, the probability   of getting 10 tails is: f(x = 10) = _______.
a 0.5000







b 0.2461







c 0.1762







d 0.1026

















The following table shows the probability distribution of the   number of days (x) to complete a certain type of construction project by a   contractor.










x f(x)







1 0.05







2 0.20







3 0.35







4 0.30







5 0.10
















3 The probability that it   will take less than 3 days to complete a randomly selected project is ______. a 0.60







b 0.45







c 0.35







d 0.25

















4 The standard deviation of   the days to complete a project is _______.   (Rounded to 2 decimal points.) a 1.03







b 1.24







c 1.35







d 1.41

















5 The   contractor's project cost is made up of a fixed cost of $20,000, plus $2,000   for each day taken to complete the project.   Expected value of total project cost is.
a $25,300







b $26,400







c $27,500







d $28,600

















6 In the previous question   the standard deviation of total project cost is:

a $22,060







b $22,828







c $2,060







d $2,828

















7 If you toss a balanced   coin 20 times, the probability   of getting 10 tails is: f(x = 10) = _______.
a 0.5000







b 0.2461







c 0.1762







d 0.1026

















Explanation / Answer

3)The probability that it will take less than 3 days to complete a randomly selected project is = P(X=1)+P(X=2)


=0.05+0.2 =0.25


so ans :d


4)The standard deviation of the days to complete a project is = sqrt(pi*(xi-xbar)^2)


substituinfg this we get standard dev =1.03


ans: a, 1.03


5) Expected value of total project cost is. =20000+2000*1*0.05+2000*0.2*2+2000*0.35*3+2000*0.3*4+2000*0.1*5


=$26,400


ans:b


6)standard deviation in above ques =1.03*2000


=2060


ans:c


7)If you toss a balanced coin 20 times, the probability of getting 10 tails is: f(x = 10) =0.5 (as there are equal chance for head and tail) =10/20 =1/2 =0.5


ans:a