1. All Urban Company produces a product requiring 4 pounds of material costing $
ID: 2503580 • Letter: 1
Question
1. All Urban Company produces a product requiring 4 pounds of material costing $3 per pound. During December, All Urban purchased 4,200 pounds of material for $11,970 and used the material to produce 500 products. What was the materials price variance for December?
a)$630 F
b)$480 F
c) $120 U
d)$600 U
2. Dillon has a standard of 1.5 pounds of materials per unit, at $2 per pound. In producing 2,000 units, Dillon used 3,100 pounds of materials at a total cost of $6,045. Dillon's materials price variance is
$350 F.
$45 U.
$155 F.
3. Dillon has a standard of 2 hours of labor per unit, at $18 per hour. In producing 2,000 units, Dillon used 3,850 hours of labor at a total cost of $70,455. Dillon's labor quantity variance is
$2,895 F.
$1,155 U.
$1,555 F.
$2,700 F.
4. The predetermined overhead rate for Zane Production Company is $10, comprised of a variable overhead rate of $6 and a fixed rate of $4. The amount of budgeted overhead costs at normal capacity of $300,000 was divided by normal capacity of 30,000 direct labor hours, to arrive at the predetermined overhead rate of $10. Actual overhead for June was $17,800 variable and $10,800 fixed, and 1,500 units were produced. The direct labor standard is 2 hours per unit produced. The total overhead variance is
$1,400 U.
$3,600 U.
$3,600 F.
$1,400 F.
5. Budgeted overhead for Cinnabar Industries at normal capacity of 30,000 direct labor hours is $4.50 per hour variable and $3 per hour fixed. In May, $232,500 of overhead was incurred in working 31,500 hours when 32,000 standard hours were allowed. The overhead controllable variance is
$3,750 favorable.
$7,500 favorable.
$7,500 unfavorable.
$1,500 favorable.
6. Budgeted overhead for Cinnabar Industries at normal capacity of 30,000 direct labor hours is $4.50 per hour variable and $3 per hour fixed. In May, $232,500 of overhead was incurred in working 31,500 hours when 32,000 standard hours were allowed. The overhead volume variance is
$6,000 favorable.
$8,250 favorable.
$3,750 favorable.
$7,500 favorable.
$350 F.
Explanation / Answer
1.) Price Variance=(Actual unit cost - Standard unit cost) * Actual Quantity Purchased=(11970/4200-3)*4200=-630
So correct option is a) $630F
2.) Price Variance=(Actual unit cost - Standard unit cost) * Actual Quantity Purchased=(6045/3100-2)*3100=-155
So correct option is c $155F
3.) Labour Quantity Variance=(Actual hours- Standard hours) * Standard Hourly Rate=(3850-2*2000)*18=-2700
So correct option is d $2700F
4.) TOTAL vARIANCE=Actual Factory Overhead - Standard Factory Overhead=
= (17800+10800)-1500*2*10=28600-30000=-1400
So corerct option is d $1400 F
5.) Overhead Controllable Variance = Actual Factory Overhead - Budgeted Allowance based on standard hours =
232500 - Standard Hours * Budgeted Variable Overhead Rate - Budgeted Fixed Overhead=232500-32000*4.5 - 90000 = -1500
Correct Option is d $1500 F
6.) [Factory overhead volume variance = Budgeted allowance based on standard hours allowed*
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.