On August 1, 2016, Reliable Software began developing a software program to allo
ID: 2501129 • Letter: O
Question
On August 1, 2016, Reliable Software began developing a software program to allow individuals to customize their investment portfolios. Technological feasibility was established on January 31, 2017, and the program was available for release on March 31, 2017. Development costs were incurred as follows:
August 1 through December 31, 2016 $6,600,000
January 1 through January 31, 2017 1,230,000
February 1 through March 31, 2017 1,630,000
Reliable expects a useful life of five years for the software and total revenues of $8,300,000 during that time. During 2017, revenue of $2,324,000 was recognized.
Required: 1. Prepare the journal entries to record the development costs in 2016 and 2017.
Explanation / Answer
December 31,2016 Research and development a/c Dr $6600000
Cash a/c $6600000
Jan 31,2017 Research and development a/c Dr $1230000
Cash a/c $1230000
March 31,2017 Research and development a/c Dr $1630000
Cash a/c $1630000
(Total development cost incurred for software)
Software a/c Dr $9460000
To Research and Development a/c $9460000
(Being software developed and was realsed on 31, March 2017)
31 December,2017
Amortization expense a/c Dr $2648800
Software a/c $2648800
(Being the amount amortized from thge greater of the two approches mentioned blow)
Percent to Revenue Approach= (Revenue of the year)/(Total revenue)* (cost of software)= $2324000/8300000*9460000= $2648800
Straigth Line Method=1/5years*9460000=$1892000
Greater one will be amortized
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.