Rodriques Tile Installation Corporation measures its activity in terms of square
ID: 2492354 • Letter: R
Question
Rodriques Tile Installation Corporation measures its activity in terms of square feet of tile installed. Last month, the budgeted level of activity was 1,630 square feet and the actual level of activity was 1,720 square feet. The company's owner budgets for supply costs, a variable overhead cost, at $3.40 per square foot. The actual supply cost last month was $6,750. In the company's flexible budget performance report for last month, what would have been the variance for supply costs? (Points : 2) $353 U $306 U $902 U $1,208 U
Explanation / Answer
Supply costs variance:
= Budgeted costs of actual activity-Actual cost of actual activity
= 1,720×$3.40-$6,750
= $902 Unfavorable
Hence, correct option is $902 U
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.