Martin Buber Co. purchased land as a factory site for $454,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months.
The company paid $47,670 to raze the old buildings and sold salvaged lumber and brick for $7,151. Legal fees of $2,100 were paid for title investigation and drawing the purchase contract. Martin Buber paid $2,497 to an engineering firm for a land survey, and $77,180 for drawing the factory plans. The land survey had to be made before definitive plans could be drawn. Title insurance on the property cost $1,703, and a liability insurance premium paid during construction was $1,022. The contractor’s charge for construction was $3,109,900. The company paid the contractor in two installments: $1,362,000 at the end of 3 months and $1,747,900 upon completion. Interest costs of $192,950 were incurred to finance the construction.
Determine the cost of the land and the cost of the building as they should be recorded on the books of Martin Buberk Co. Assume that the land survey was for the building.
Cost of the Land $ Cost of the Building $Explanation / Answer
Cost of Land = Purchase cost + Land survey = 454000 + 2497 = $456497
Cost of Building = Razing old building - Sale of lumber and brick + Legal fees + Drawing of factory plans + Insurance cost + Liability insuance premium + Construction charge + Interest cost
= 47670 - 7151 + 2100 + 77180 + 1703 + 1022 + 3109900 + 192950
= $3425374