Problem A Jazzy Jeans uses standard costing in their accounting system. They hav
ID: 2486649 • Letter: P
Question
Problem A
Jazzy Jeans uses standard costing in their accounting system. They have developed the following standards for men's jeans
Std Qty Std Price
Direct materials (yards) 2 18.00 per yard
Direct labor (hours) 0.5 20.00 per hour
During November, Jazzy produced 10,000 pairs of jeans.
Activity for the month was:
Quantity Total cost
Purchased material (in yards) 24,000.00 428,400.00
Material used 20,500.00
Hours worked by direct laborers 5,250.00 100,800.00
1. What was the material price variance for the month?
2. What was the materials quantity variance for the month?
3. What was the labor efficiency variance for the month?
4. What was the labor rate variance for the month?
Problem B
Jazzy Jeans applies manufacturing overhead using machine hours as the cost driver.
Fixed MOH costs are budgeted at $1,000,000 per month.
Variable MOH costs are budgeted at $52.80 per machine hour.
It takes .25 machine hours to produce a pair of jeans.
Jazzy budgeted production of 10,000 pairs of Jeans in December.
Actual activity in December:
Total Variable MOH Costs 134,767.50
Total Fixed MOH Costs 988,000.00
Actual pairs of jeans made 10,500
Actual machine hours 2,550
5. What was the variable overhead spending variance for the month?
6. What was the variable overhead efficiency variance for the month?
7. How much fixed MOH was applied in December?
8. What was the fixed overhead spending variance for the month?
9. What was the fixed overhead volume variance for the month?
Show your work in all your answers.
Please can I have your help.... Thank you sooo much....
Explanation / Answer
There are 2 different problem so I will answer only problem A with all its subparts.
(1) Material price variance = (SP – AP) AQ
= (18 – 17.85) x 20500 = $3075 (Favaorable)
(2) Material quantity variance = (SQ – AQ) SP
= (20000 – 20500) x 18 = $9000 (Unfavaorable)
(3) Labor efficiency variance = (SH – AH) SR
= (5000 – 5250) x 20 = $5000 (Unfavaorable)
(4) Labor rate variance = (SR – AR) AH
= (20 – 19.2) x 5250 = $4200 (Favaorable)
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.