#32:[Required| 15points Asswer in grid & show work on back of page Slumber Compa
ID: 2486503 • Letter: #
Question
Explanation / Answer
(A)
Compute NPV
PAyback Calculation
In the fourth year we recived total 170,000
so year 3 + some days of 4th year
=20,000*365/50,000
=146
So poayback period is 3 year and 146 days
In the fourth year we recived total 100,000
so year 3 + some days of 4th year
=10,000*365/30,000
=122
So poayback period is 3 year and 122days
As per NPV calculation we should select project A because it has higher NPV
2
If we do not discount the Cash flow then project B is Better because it has higher return
C)
The other metrics that is missing is IRR .With the help of IRR we could take the decesion . That poject will be selected which has higher IRR
Slumber compant Alternative 1 Alternative 2 Initial Investment 170,000 100,000 Estimated Aftertax Cash flow 50,000 30,000 PV factor for 5 year 3.7909 3.7909 PV of cash Flow 189545 113727 Prasent Value= PV of Cash Flow-initial Investment 19,545 13,727
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.