Bubb Corporation has provided the following data from its activity-based costing
ID: 2484755 • Letter: B
Question
Bubb Corporation has provided the following data from its activity-based costing accounting system:
Activity Cost Pools Total Costs Total Activity
Designing products---------- $806,715 6,895 product design hours
Setting up batches---------- 23,660 910 batch set ups
assembling products-------- 42,240 3,520 assembly hours
Required:
Compute the activity rates for each of the three cost pools. Show your work!
Explanation / Answer
Activity rates = total cost / total activity
Activity cost pools total costs total activity Activity rates Designing products $ 8,06,715.00 6895 $ 117.00 per product design hours Setting up batches $ 23,660.00 910 $ 26.00 perbatch set ups assembling products $ 42,240.00 3520 $ 12.00 per assembly hoursRelated Questions