Beldon Corporation purchased land as a factory site for S63.DOO. An ok) building
ID: 2484329 • Letter: B
Question
Beldon Corporation purchased land as a factory site for S63.DOO. An ok) building on the property was demolished, and construction began on a new building that was completed on December 15. 2016. Costs incurred during this period are listed below: Salvaged materials resulting from the demolition of the old building were sold for $2.300. Determine the amounts that Beldon should capitalize as the cost of the land. (Amounts to be deducted should be indicated with a minus sign.) Determine the amounts that Beldon should capitalize as the cost of the new building.Explanation / Answer
Computation of the Capitalize cost of the land and New Building
Cost of land:
Particulars Amount
Land $ 63,000
Demolition $ 5,500
Legal fees $ 3,500
Salvage materials $ (2,300)
Cost of Land $ 69,700
------------------------------------------------------------------------------------------------------------
Cost of building:
Particulars Amount
Construction costs $ 530,000
Interest on construction loan $ 6,500
Architect $ 15,000
Cost of Building $ 551,500
Property tax is recurring Expenditure ,hence it should be expensed out ,should not be capitalized.
Hence the cost of building and cost of land is $ 551,500 $ 69,700