Mahler, Inc., applies manufacturing overhead at the rate of $40 per machine hour
ID: 2476192 • Letter: M
Question
Mahler, Inc., applies manufacturing overhead at the rate of $40 per machine hour. Budgeted machine hours for the current period were anticipated to be 120,000; however, a lengthy strike resulted in actual machine hours being worked of only 90,000. Budgeted and actual manufacturing overhead figures for the year were $4,800,000 and $4,180,000, respectively. On the basis of this information, the company's year-end overhead was:
a)underapplied by $580,000.
b)overapplied by $1,200,000.
c)underapplied by $1,200,000.
d)underapplied by $900,000.
e)overapplied by $580,000.
Explanation / Answer
On the basis of the given information, the company's year-end overhead was: option a)underapplied by $580,000.
Explanation:
Given information, Estimated total overhead costs – $4,800,000
Estimated total Machine hours – 120,000
Predetermined overhead rate – $40 per Machine hour
Actuals:
Actual overhead cost– $4,180,000
Actual Machine hours – 90,000
In this case, the Underapplied overhead will be $580,000 and it is calculated as follows.
Step 1 – Calculate the overhead that was applied by taking the actual Machine hours incurred times the predetermined overhead rate. 90,000 x $40 = $3,600,000
Step 2 – Compare actual manufacturing costs to the applied overhead for the accounting period = $4,180,000 - $3,600,000 = $580,000 Under applied.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.