Magnum Incorporated began operations in July of the current year. Magnum uses th

ID: 2485428 • Letter: M

Question

Magnum Incorporated began operations in July of the current year. Magnum uses the job order cost system and applies overhead to jobs on a basis of $15 per machine hour. The following information is for July:

Direct materials cost

Direct labor cost

Machine hours

Job 20

$1,200

$10,200

90

Job 21

$1,025

$8,000

80

Job 22

$2,200

$9,180

120



Jobs 20 and 22 have been completed. The balance is work-in-process inventory on July 31 is

Direct materials cost

Direct labor cost

Machine hours

Job 20

$1,200

$10,200

90

Job 21

$1,025

$8,000

80

Job 22

$2,200

$9,180

120

Explanation / Answer

Here job 20 and 22 is completed . So it means that job 21 is work in progress.

So work in progress will be as follow-

Direct Material= $1025

Direct Labour Cost=$8000

Overhead cost ( (80*15)=$1200

Total work in progress as on july 31 is= $10225