Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

a. Calculate the landfill project’s internal rate of return to the nearest whole

ID: 2470431 • Letter: A

Question

a. Calculate the landfill project’s internal rate of return to the nearest whole percent.

Jefferson County's Board of Representatives Is considering the purchase of a site for a new sanitary landfill. The purchase price for the site is $190,000 and preparatory work will cost $69,900. The landfill would be usable for 10 years. The board hired a consultant, who estlmated that the new landfill would cost the county $46,000 per year less to operate than the county's current landfill. The current landfill also will ast 10 more years. For a landfill project, Jefferson County can borrow money from the federal government at a subsldized rate. The county's hurdle rate is only 8 percent for this project. Use Appendix A for your reference. (Use appropriate factorfs) from the tables provided.)

Explanation / Answer

Savings in operating costs per year = $46000

Initial investment = $190000 + $69900 = $259900

NPV at 10%:

NPV = $46000 x PVIFA (10%, 10) -$259900 = $46000 x 6.14456 - $259900 = $22750

NPV at 20%:

NPV = $46000 x PVIFA (20%, 10) -$259900 = $46000 x 4.19247 - $259900 = -$67046

IRR is the discount rate at which NPV is zero

Rate

NPV

10%

22750

R

0

20%

-67046

By interpolation we get

R = 10% + 10% * ((0-22750)/(-67046-22750) = 13%

As hurdle rate is 8%, and IRR is 12.53%, the project should be accepted.

Rate

NPV

10%

22750

R

0

20%

-67046

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote