1.0 i need two things was 25.4 what is Manufacturing cycle time ? and Value-adde

ID: 2469699 • Letter: 1

Question

1.0

i need two things

was 25.4

what is Manufacturing cycle time ? and Value-added time ?

Days Required Process customer order 0.2 Wait for direct materials to arrive 2.0 Fabrication of parts 4.0 Move order to assembly department 0.8 Wait for machine time 7.0 Assembly of parts 2.0 Move order to finishing department 0.5 Wait for machine time 2.0 Finishing of units 4.0 Move to packing department 0.5 Packing 1.6 Move to shipping department 0.2 Load delivery truck 0.6 Drive to customer 1.5 Unload delivery truck 0.9 Return to plant

1.0

Explanation / Answer

Manufacturing cycle time: The amount of time required to turn raw materials into completed product is called throughput time, or Manufacturing cycle time and is calculated in the following manner:

Manufacturing cycle time = Process time + Inspection time + move time + queue time

= 0.2 + 0.8 + 0.5 + 0.5 + 0.2 + 2 + 7 + 2

= 13.2

Value-added time: Value added time is the time spent on improving the outcome of a process. This is typically just the processing time associated with production. All of the other intervals associated with a process, such as wait time and queue time, contribute nothing to the outcome and so are considered non-value added time.

Value added time = 0.2 + 4+ 2 + 4 + 1.6 = 11.8