On March 1, 2016, Beldon Corporation purchased land as a factory site for $60,00
ID: 2467923 • Letter: O
Question
On March 1, 2016, Beldon Corporation purchased land as a factory site for $60,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2016. Costs incurred during this period are listed below: Demolition of old building Architect's fees (for new building) Legal fees for title investigation of land Property taxes on land (for period beginning March 1, 2016) Construction costs Interest on construction loan $4,000 12,000 2,000 3,000 500,000 5,000 Salvaged materials resulting from the demolition of the old building were sold for $2,000. Required: 1-a. Determine the amounts that Beldon should capitalize as the cost of the land. (Amounts to be deducted should be indicated with a minus sign.) Capitalized cost of land: Total cost of landExplanation / Answer
1-a.Capitalized cost of land:
Particulars Amount
Land $ 60,000
Demolition $ 4,000
Legal fees $ 2,000
Salvage materials - $ 2,000
Total Cost of Land $ 64,000
1-b. Capitalized Cost of building:
Particulars Amount
Construction costs $ 500,000
Interest on construction loan $ 5,000
Architect $ 12,000
Total Cost of Building $ 517,000
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.